Bissett Lake Project - As you can see from the attached photos, the bridge has arrived in Dartmouth and will be placed Monday afternoon. This should allow the project to be completed by mid-December. The schedule:


  • Bridge placement Nov. 19.
  • Finish bridge connections Nov. 21
  • Complete gravel build up to boardwalk Nov. 24
  • Boardwalk completed Dec 8
  • Final crusher dusting  & rolling Dec. 12-14